Laying pipe on the seafloor can pose a number
of challenges, especially if the water is deep. There are three main ways that
subsea pipe is laid -- S-lay, J-lay and tow-in -- and the pipelay vessel is
integral to the success of the installation.
Buoyancy affects the pipelay process, both in
positive and negative ways. In the water, the pipe weighs less if it is filled
with air, which puts less stress on the pipelay barge. But once in place on the
sea bed, the pipe requires a downward force to remain in place. This can be
provided by the weight of the oil passing through the pipeline, but gas does
not weigh enough to keep the pipe from drifting across the seafloor. In
shallow-water scenarios, concrete is poured over the pipe to keep it in place,
while in deepwater situations, the amount of insulation and the thickness required
to ward of hydrostatic pressure is usually enough to keep the line in place.
Tow-In Pipeline
Installation
While jumpers are typically short enough to be
installed in sections by ROVs, flowlines and pipelines are usually long enough
to require a different type of installation, whether that is tow-in, S-lay or
J-lay.
Tow-in installation is just what it sounds
like; here, the pipe is suspended in the water via buoyancy modules, and one or
two tug boats tow the pipe into place. Once on location, the buoyancy modules
are removed or flooded with water, and the pipe floats to the seafloor.
There are four main forms of tow-in pipeline
installation. The first, the surface tow involves towing the pipeline on top of
the water. In this method, a tug tows the pipe on top of the water, and
buoyancy modules help to keep it on the water's surface.
Using less buoyancy modules than the surface
tow, the mid-depth tow uses the forward speed of the tug boat to keep the
pipeline at a submerged level. Once the forward motion has stopped, the pipeline
settles to the seafloor.
Off-bottom tow uses buoyancy modules and chains
for added weight, working against each other to keep the pipe just above the
sea bed. When on location, the buoyancy modules are removed, and the pipe settles
to the seafloor.
Lastly, the bottom tow drags the pipe along the
sea bed, using no buoyancy modules. Only performed in shallow-water
installations, the sea floor must be soft and flat for this type of
installation.
S-Lay Pipeline
Installation
When performing S-lay pipeline installation,
pipe is eased off the stern of the vessel as the boat moves forward. The pipe
curves downward from the stern through the water until it reaches the
"touchdown point," or its final destination on the seafloor. As more
pipe is welded in the line and eased off the boat, the pipe forms the shape of
an "S" in the water.
Stingers, measuring up to 300 feet (91 meters)
long, extend from the stern to support the pipe as it is moved into the water,
as well as control the curvature of the installation. Some pipelay barges have
adjustable stingers, which can be shortened or lengthened according to the
water depth.
Proper tension is integral during the S-lay
process, which is maintained via tensioning rollers and a controlled forward thrust,
keeping the pipe from buckling. S-lay can be performed in waters up to 6,500
feet (1,981 meters) deep, and as many as 4 miles (6 kilometers) a day of pipe
can be installed in this manner.
J-Lay Pipeline
Installation
Overcoming some of the obstacles of S-lay
installation, J-lay pipeline installation puts less stress on the pipeline by
inserting the pipeline in an almost vertical position. Here, pipe is lifted via
a tall tower on the boat, and inserted into the sea. Unlike the double
curvature obtained in S-lay, the pipe only curves once in J-lay installation,
taking on the shape of a "J" under the water.
The reduced stress on the pipe allows J-lay to
work in deeper water depths. Additionally, the J-lay pipeline can withstand
more motion and underwater currents than pipe being installed in the S-lay
fashion.
Types Of Pipelay
Vessels
There are three main types of pipelay vessels.
There are J-lay and S-lay barges that include a welding station and lifting
crane on board. The 40- or 80-foot (12- or 24-meter) pipe sections are welded
away from wind and water, in an enclosed environment. On these types of
vessels, the pipe is laid one section at a time, in an assembly-line method.
On the other hand, reel barges contain a
vertical or horizontal reel that the pipe is wrapped around. Reel barges are
able to install both smaller diameter pipe and flexible pipe. Horizontal reel
barges perform S-lay installation, while vertical reel barges can perform both
S-lay and J-lay pipeline installation.
When using reel barges, the welding together of
pipe sections is done onshore, reducing installation costs. Reeled pipe is
lifted from the dock to the vessel, and the pipe is simply rolled out as
installation is performed. Once all of the pipe on the reel has been installed,
the vessel either returns to shore for another, or some reel barges are
outfitted with cranes that can lift a new reel from a transport vessel and
return the spent reel, which saves time and money.
Source: https://www.linkedin.com/pulse/how-does-offshore-pipeline-installation-work-huzaifa-bw
This was a perfectly nice experience to go through the pipeline installation. Learned various methods of pipeline plantation. Heating and Cooling Newmarket
ReplyDeleteThese kind of post are much needed for our know how.Heating and Cooling Toronto
ReplyDeleteSome people don't consider space size before selecting a specific air conditioner.
The chemical process defined here for developing a better AC are really great.Heating and Cooling Richmond Hill These kind of processes always works out.
ReplyDelete